Position of projects being executed by C-D&D
       

Achievements in the month of October ’17
 
1. Validation of new partial cab redundancy software in 11 locomotives at ELS/LGD.
 
2. Commissioning of Hotel load converters of M/s Siemens make with modified scheme of filter cubicle implemented in Loco Nos. 30590, 30591,30593, 30594, 30600 & 30601.
 
3. TCN based C-DAC VCU manufactured by ToT partners commissioned in Loco Nos. 31967, 31968, 32014 & 32080.
 
4. Commissioning & testing of M/s BTIL make IGBT based propulsion system in loco Nos. 31992 and M/s Medha make on Loco Nos. 30590, 30594, 30132, 30591 & 30601.
5. Commissioning & testing of M/s BHEL make IGBT based full propulsion system in loco Nos. 32008, 30593, 31975, 32012, 32013 & 31970.
Targets for the month of November ’17
 
1.     Commissioning & testing of M/s ARC make DPWCS in loco No. 32101.
 
2.     Commissioning of Crew voice & video recording system in loco No. 32101.
 
3.     Scrutiny and approval of design document of Hotel Load converter for WAP-7 Locomotive for new entrants.
 
4.     Scrutiny of Proforma-A & compliance to STR of 3-ph drive Propulsion System of new entrants.
 
5.     Commissioning and testing of Hotel load converters of M/s Medha make on loco Nos. 30575, 30576,30579,30580,30581 and M/s Siemens make on Loco No. 30588, 30608, 30609 & 30614.
 
6. Commissioning & testing of M/s BHEL make IGBT based full propulsion system in loco Nos. 30597, 30598,30621,30625,31964. And M/s Medha make on 30602,30603 & 30608.
 
 
Detailed project position is enclosed:
 

   STATUS OF ON GOING PROJECTS at C-D&D AS ON 01.11.2017
  

SN
Project
Status
1.
Centre of Excellence at CLW
·     Total 04 projects have been envisaged under Centre of Excellence at CLW:
 Project-1: (a) Center for Simulation and Evaluation of Suspension/ Bogie & Traction System
(b) Electric loco modeling, virtual modeling and simulation
Project-2: Laboratory for Development and evaluation of Power Electronics Applications (Setting up of PCB Lab)
Project-3:Software development Lab
Project-4:Laboratory for development and evaluation of Electrical Insulation Materials
·     Specifications for all projects finalized.
·     Detailed estimated sanctioned by GM/CLW.
·     NSR approved by Finance.
·     Special Conditions for Contract & Eligibility Criteria for all 04 projects prepared and approved by competent authority.
·     All cases forwarded to store for procurement.
·     Pre-bid conference held on 24.4.2017.
·     Tenders for all projects opened on 31.5.2017.
·     TR for all projects finalized. TC under finalization.
 
2.
Multi Traction Hybrid Passenger Locomotive (MTHPL)
·     A total 05 (five) Locomotives sanctioned by Railway Board (vide RSP 2016-17, Item No.1161).
·     Functional requirement Specification (FRS) prepared by RDSO.
·     Pre-application conference held on 19.03.2016 to facilitate the prospective manufacturers.
·     Expression of Interest (EOI) floated by CLW and 6 offers received.
·     Specification and Special Conditions of Contact finalized.
·     Detailed estimate and NSR approved.
·     Tender opened on 26.05.2017.
·     TR finalized. TC under finalization.

 

Sl. No
Project
 
Firm’s Name
P.O. No. / LoA No. & DP
Order
Qty.
Status
3.
Up gradation of WAG-9H locomotive to 9000 HP
Siemens
As per Specification No. RDSO/2017/EL/SPEC/0127Rev’0’ and SCC no. CLW/C-D&D/0549/SCC Rev’0’
LOA No. 70/18/1145(GT) dated: 20.09.2017
Original DP-As per the modalities given in the clause no. 3.0 of Clw SCC
Corrigendum-Railway Reserves the right to order other variant(Passenger loco) in addition to freight loco.
 
5
Supply yet to commence.
Medha
As per Specification No. RDSO/2017/EL/SPEC/0127Rev’0’ and SCC no. CLW/C-D&D/0549/SCC Rev’0’
Counter  offer No. 70/18/1145(GT) dated: 20.09.2017
5
Supply yet to commence.
CGL
As per Specification No. RDSO/2017/EL/SPEC/0127Rev’0’ and SCC no. CLW/C-D&D/0549/SCC Rev’0’
Counter  offer No. 70/18/1145(GT) dated: 20.09.2017
5
Supply yet to commence.
4.
Development of Hotel Load converter for WAP-7 Locomotive.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Siemens
P.O. No. 70/16/1125/ 10824 dated: 20.9.2016.
Amendment 02
Quantity increased from 17 loco sets to 22 locosets against 30% option clause.
17
sets
+05
sets
 
 
Material for all loco sets received at CLW.
Commissioned in loco nos. 30590,30591, 30593,30594,30600 & 30601 in October’ 17
P.O. No. 70/19/1125/11150 dated: 30.08.2017.
Original DP: Prototype unit: 09 sets/month from P.O.
49 sets
Design document against Alt. D approved.
 
26 sets received at CLW.
 
Medha
 
P.O. No. 70/16/1125/ 10859 dated: 05.10.2016.
 
26 sets
All loco sets received at CLW.
Loco Nos. 30570, 30573, 30577 & 30578dispatched in August’17 from CLW.
Under commissioning on loco Nos. 30575, 30576, 30579 & 30580, 30581
PO No. 70/18/1125/11151 dated. 30/08/09.
Original DP: From the date of P.O @minimum 6 sets per month
33 sets
Supply yet to commence.
AAL
PO No. 70/2008/1125/ 00079 dt. 30/07/09
Original DP: Prototype unit: Within 01 year from P.O.
Extended DP:Extended up to 09.03.2015.
03 sets
Prototype unit commissioned on loco No. 30502 and dispatched to ELS/GZB in Nov’16.
Balance set to be supplied after field trial.
P.O. issued.
01 set
Supply yet to commence.
 
BHEL
PO No. 70/2008/1125/ 00081 dt. 05/08/09
Original DP: Prototype unit: Within 12 months from P.O.
1 Set
1st set commissioned on loco No. 30426 and dispatched to ELS/RPM in Aug.’15.
Field trials with dual hotel windings completed at Bangalore/Chennai alongwith RDSO.
PO No. 70/11/1125/00363
Dated: 02.08.12
Original DP: Prototype unit: Within 09 months from approval of design from RDSO.
03 sets
All loco sets received at CLW.
Under Commissioning in loco Nos. 30643, 30644 & 30645.
 
 
70/16/1125/10823 dated: 20.9.2016.
Original DP Within 2 months from P.O. and @ 10 sets per quarter.
32
sets
Design document submitted against alteration C.
 
PO No. 70/18/1125/11152
Dated: 30.08.17
Original DP: To commence within 2 months from the date of clearance by CEE/D&D against earlier order @ minimum 3 sets per month.
17 sets
Supply yet to commence.
ABB
PO No. 70/11/1125/00344
Dated: 7.5.12
Original DP: Prototype unit: Offer of Prototype 03 months from approval of design.
Series Supply: @ 02 sets/ month.
03 sets
 
Prototype Unit commissioned on Loco No. 30510 and dispatched to ELS/BRCY in Dec’16.
01 set
Loco No. 30510 running in service for field performance
P.O. issued.
01 set
Supply yet to commence.
HIRECT
PO No. 70/16/1125/11005
Dated: 06.3.17
 
03 set
Design document against Alt. C under scrutiny.
P.O. issued.
01 set
Supply yet to commence.
Trolex
LOA No. 70/15/1125A
Dated: 13.4.2015.
01 set
Under firm assessment.
5.
Provision of Crew voice & video recording system on 3-ph passenger locomotives.
 As per Specn No.
RDSO/2015/EL/SPEC/0118 [Rev ’0’].
Trolex
P.O. No. 34/2017/2972/ 38096 dated: 21.08.2017.
Prototype unit:Prototype 03 months from the date of P. O.
Series Supply:Remaining sets within 06 months from prototype inspection i.e by 31.05.2018.
10 sets
Supply yet to commence.
Kayson
P.O issued.
5 sets
Supply yet to commence
Elixir
P.O issued.
3 sets
Supply yet to commence
6.
Indigenous development of IGBT based propulsion system.
 
Specification No. RDSO/2008/EL/
Spec/0071 Rev.5 issued in June’2016.
Medha
PO No. 70/12/1134/08209
dated: 07.05.12
 
05 sets
All Loco sets dispatched.
1st set commissioned on loco No. 31427 dispatched to ELS/LGD on 31.10.2013.
PO No. 70/14/1134/10402 dated: 12.8.2015.
24 sets
All Loco sets dispatched.
 
PO No. 70/16/1134/10869 dated: 20.10.2016.
Original DP: 1st 02 sets within 5 months. Balance qty. after 6 months @ 10 sets per quarter.
48 sets
Total 42 Loco sets supplied.
36 loco sets dispatched.
06 loco sets (loco Nos. 31949, 32002 & 32003, 30586, 30587 & 30589) dispatched from CLW in September’17.
Loco Nos. 30590, 30594, 30132,30591 & 30601
 dispatched from CLW in October’17.
ABB
PO No. 70/14/1134/10413 dated: 01.9.2015.
DP: Prototype unit: Within 06 months from P.O.
Series Supply: After approval of field trial by RDSO and to be completed within a quarter thereafter.
03 sets
Supply yet to commence.
PO No. 70/16/1134/10879 dated: 11.11.2016.
DP:Within 12 months from P.O.
01 set
Prototype unit commissioned on loco no. 31936 and dispatched in June’2017.
PO No. 70/17/1134/11054 dated: 19.05.2017.
DP:Within 06 months from P.O. @ 10 sets per quarter. To be completed by Feb’18.
17 sets
One set received at CLW.
PO No. 70/18/1134/11246 dated: 25.10.2017.
DP:To commence within 4th month from the date of order and to be completed within 6 months of commencement of supply or 10 months of order whichever is earlier @12 sets /month
64 sets
Supply yet to commence.
BHEL
PO No. 70/14/1134/10414 dated: 01.9.2015.
 
06 sets
All Loco sets dispatched.
 
PO No. 70/17/1134/11053 dated: 19.05.2017.
DP:Within 03 months from P.O. @ 10 sets per month.
66 sets
16 sets received at CLW.
Commissioned in loco Nos.32008,30593,31975,32012,32013 & 31970 in October’17
PO No. 70/18/1134/11240 dated: 23.010.2017.
Supply shall commence within 4th month from the date of order & would be completed within 6 months of commencement of supply or 10 months of order date whichever is earlier
 
95 sets
Supply yet to commence.
Siemens
PO No. 70/14/1134/10570 dated: 04.2.2016.
DP:Within 12 months from P.O.
01 set
Design document submitted.
Supply yet to commence.
CGL
PO No. 70/16/1134/10892 dated: 25.11.2016.
Original DP:
Within 9 months from P.O.
01 set
Loco No. 31957 dispatched to ELS/GMO in July’17.
BTIL
PO No. 70/16/1134/10950 dated: 17.01.2017.
Original DP:Within 15 months from P.O.
01 set
Commissioned in Loco No. 31985.
 
PO No. 70/18/1134/02/ 11104 dated: 08.07.2017.
DP: Within July’2017 preferably by 20 July’2017 urgently.
05 sets
Commissioned in loco Nos. 31989, 31994, 31995 & 31996 in September’ 17.
Commissioned in Loco No. 31992in October’ 17
 
PO No. 70/18/1134/02/ 11241 dated:23.10.2017
To commence 4-5 months from the date of P.O and to be supplied @14-16 sets per month
30 sets
Supply yet to commence
 
Developmental order has been placed for 01 loco-set each on following firms:
a.      M/s CRRC Pioneer Electric India Pvt. Ltd./Rewari/Haryana
b.      M/s Titagarh Wagons Ltd./Kolkata
c.       M/s Hind Rectifier/Mumbai
d.      M/s Delta Power solutions India Pvt. Ltd./Rudrapur/Uttaranchal
e.      M/s Advance Rail Controls Pvt. Ltd./Bangalore
 
·           M/s Delta Power solutions India Pvt. Ltd. has submitted Proforma-A & compliance to STR. Under scrutiny at CLW.
·           Design document of M/s CRRC under scrutiny.
7.
Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (200 Kmph)
(Rly. Bd’s L/No. 2007/Elect (TRS)/440/15 dated: 26.02.09).
 
 
M/s Arihant Electricals
Kol.
P.O. No. 91/10/0945/NS/ 00135 dated: 09/06/10
Original DP:
Prototype unit: 1 loco set within 06 months from PO.
Series Supply:
After 03 months from successful clearance of prototype for 06 months.
Extended DP: upto 31.3.14
2 sets
Prototype unit commissioned on loco No. 30086. Loco dispatched to ELS/GZB in Oct’15.
Field trial report of prototype unit received at CLW.
Dispatch clearance given for 2nd unit.
Supply of 2nd set yet to commence.
 
8.
Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (160 Kmph).
 
 
M/s Arihant Electricals
Kol.
P.O. No. 91/10/0943/ 00096 dt.12/03/2010
Original DP: Prototype unit: 05 Nos. within 06 months from PO.
Series Supply: After 03 months from successful clearance of prototype for 18 months.
Extended DP: DP extended upto 31.3.15.
05  sets
Prototype unit commissioned in Loco No. 30056. Loco under commercial service since Dec’12 under ELS/BRCY.
2nd, 3rd and 4th set commissioned on loco No. 30087, 30090 & 30100 and sent to ELS/BRCY in Nov’15 & Jan’16 and ELS/GZB in March’16 respectively.
Supply of 03 Nos. yet to commence.
Tender for 20 loco sets opened on 31.05.2017. TR finalized. TC under finalization.
9.
Indigenous development of TCN compliant vehicle control system through C-DAC.
(Pink Book No. 66 of 2012-13.)
C-DAC
MOU no. L 901118
dated 31/8/07
Original DP:
Project duration: 30 months.
 
 
02 sets
Commissioning has been completed in loco No. 31356 (WAG-9H). Loco dispatched to ELS/TKD. Performance found satisfactory.
Agreement for Transfer of Technology signed by CGL, ABB, AAL and BHEL with C-DAC.
2nd unit commissioned in loco No. 31778 and dispatched in August’16
10.
Vehicle Control Unit based on TCN open standard for 3-phase locomotives as per CLW specification No. CLW/C_D&D/ ES/3/TCN/0547 Dated: May’2016.
M/s ABB
P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype.
P.O. to be completed by 31.03.2018.
02 sets
 +02 sets
Commissioned in Loco Nos. 31951 & 31988.
Further one set received at CLW.
Commissioned in Loco No. 32014 in October’17
 
 
P.O. No. 70/18/1142/ 11195 dated: 15.09.2017.
Delivery: 10 sets by October 2017.Balance @10 sets per month
TDP- January 2018
34 sets
10 sets received at CLW.
M/s BHEL
P.O. No. 70/16/1142/ 11002 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype. P.O. to be completed by 31.03.2018.
03 sets
To be increased to 06 sets
Supply yet to commence.
P.O. No. 70/17/1142/ 11077 dated: 17.06.2017
Prototype unit: Within 06 months from PO.
Series Supply: 12 sets per quarter thereafter.
42 sets
Supply yet to commence.
P.O. No. 70/18/1142/ 11230 dated: 09.10.2017
To start within 03 months from date of P.O. @05 sets per month,to be completed by 31.03.2018.
23 sets
Supply yet to commence
M/s CGL
P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype.
P.O. to be completed by 31.03.2018.
05 sets
to be increased to 10 sets
1st unit commissioned in loco No. 30577 and dispatched to ELS/LGD in August’17.
Further 03 sets commissioned on loco Nos. 31967,31968 & 32080 in October’17
 
 
 
P.O. No. 70/17/1142/ 11078 dated: 17.06.2017
Delivery: To commence from 01.04.2008 and would be completed by 31.12.2018.
28 sets
15 sets received at CLW.
11.
Remote Monitoring System for 3-phase Electric Locomotives (Specification No.
C-D&D/ES/3/0546)
 
 
 
150 sets
Tender opened on 10.05.2017.
Under finalization.
 
12.
Development of Distributed Power Wireless Control System (DPWCS)for 3-phase electric loco. (P.B. item No. 37/ 2012-13.) Rly. Bd’s L/No. 2003/ Elect (TRS)/441 /8 dt. 29.12.06)
P.B. item no. 358/2012-13, 1122/2012-13.
M/s. ARC/
B’lore
LoA No. OT/ C-D&D/01/07/ 2007-08 dated 3rd June, 2008.
 
2 pair of locos
The prototype pairs have been installed in loco nos. 31282 (WAG-9) & 31284 (WAG-9). Loco has been put into commercial service w.e.f. 18.05.2012.
2nd set has been installed on Loco No. 31525 & 31526 and dispatched to ELS/TATA in Nov.’14.
Field trials completed. RDSO to give final clearance.
 
P.O. No. 70/16/1140/01088 dated: 28.06.2017.
Original DP:
Prototype unit: Within 06 months from PO.
Series Supply: @ 10 sets /month.
45 sets
Design document approved.
1st set received at CLW.
Under commissioning on loco No. 32101.
 
GE
P.O. No. 70/16/1140/01090 dated: 28.06.2017.
Prototype unit: Within 06 months from PO.
Series Supply: Within 06th month of prototype clearance and to be completed by 12 months after issuance of P.O.
10 sets
Supply yet to commence.
Lotus
P.O. No. 70/16/1140/01089 dated: 28.06.2017.
Prototype unit: Within 06 months from the date of P.O. delivery.
Series Supply: @ 10 sets /month from 6th month of prototype clearance
20 sets
Design Document submitted. Under scrutiny at CLW.
13.
IGBT based Composite Converter with Traction Converter and Hotel Load Converter for 3-ph WAP-5 locomotives as per Specification No. CLW/ES/IGBT/ 0518 Alt. B
ABB
P.O. No. 70/16/1136/ 10994 dated: 25.02.2017.
Original DP:
Prototype unit: Within 10 months from PO.
Series Supply: After 06 months from date of clearance of prototype.
10 sets
 
Mechanical dimension & basic design submitted by firm. Design document approved.
Supply yet to commence.
1st set expected to deliver at CLW in November’17.
CGL
P.O. No. 70/16/1136/ 11016 dated: 23.03.2017.
Original DP:
Prototype unit: Within 12 months from PO.
Series Supply: After 03 months from date of clearance of prototype @ 3 sets /quarter.
05 sets
 
Supply yet to commence.
BHEL
P.O. No. 70/16/1136/ 10995 dated: 25.02.2017.
Original DP:
Prototype unit: Within 12 months from PO.
Series Supply: After clearance of prototype @ 2 sets /quarter.
05 sets
 
Supply yet to commence.
 

 
 

 



Source : Welcome to CLW Official Website ! CMS Team Last Reviewed on: 06-11-2017  

  Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.