Position of projects being executed by C-D&D
     

Achievements in the month of August ’17

 

1.  Regular cut-in of locomotives with Hotel Load Converter and without Contactor No. 32 & Relay No. 33 in its filter cubicle.

 

2.  1st unit of TCN based C-DAC VCU of M/s CGL make commissioned in loco No. 30577 and dispatched to ELS/LGD.

 

3.  Technical evaluation of tender case of Alternate Driving Gear System for WAP-5 locomotives.

 

4.  Scrutiny and approval of test protocol, GA layout drawing and BOM of Hotel Load converter for WAP-7 Locomotive for M/s Medha & M/s Trolex.

 

5.  Expression of Interest (EOI) floated for Complete Pantograph for 3-phase locomotives.

 

6.  Commissioning of Hotel load converters of M/s Medha make on Loco Nos. 30570, 30573, 30577 & 30578.

7.  Commissioning of M/s Medha make propulsion system on Loco Nos. 31938, 31939, 30942, 31961, 31945, 31948 & 31962.  

 

Targets for the month of September ’17

 

1.     Commissioning & testing of M/s ARC make DPWCS in loco No. 32101.

 

2.     Commissioning & testing of M/s BTIL make IGBT based propulsion system in loco Nos. 31985, 31989, 31992, 31994, 31995 & 31996.

 

3.     Design Document approval for new entrants for composite converter with Hotel Load for WAP-5 Locomotive.

 

4.     Scrutiny of test protocol of DPWCS for new entrants.

 

5.     Scrutiny and approval of design document of Hotel Load converter for WAP-7 Locomotive for new entrants.

 

6.     Scrutiny of Proforma-A & compliance to STR of 3-ph drive Propulsion System of new entrants.

 

7.     Uploading of Expression of Interest (EOI) for Repair/Rehabilitation of motorized bogie of 3 phase locomotives at Loco sheds.

 

Detailed project position is enclosed:

 

 


STATUS OF ON GOING PROJECTS at C-D&D AS ON 01.09.2017

SN

Project

Status

1.

Upgradation of WAG-9H locomotive to 9000 HP

·     Functional requirement Specification (FRS) prepared.

·     Expression of Interest (EOI) uploaded on CLW website.

·     Pre-application conference held on 30.09.2016 & 07.10.2016 at CLW for better appreciation and clarification.

·     Estimate finalized.

·     Meeting held at Railway Board on 10.3.2017 between Rly. Board, prospective bidders, RDSO & CLW.

·     Specification finalized by RDSO.

·     Special condition of contract (SCC) and eligibility criteria finalized.

·     Estimate prepared and approved by GM/CLW.

·     NSR prepared and approved.

·     Tender opened on 11.07.2017.

·     TR finalized. TC under finalization.

2.

Centre of Excellence at CLW

·     Total 04 projects have been envisaged under Centre of Excellence at CLW:

 Project-1:  (a) Center for Simulation and Evaluation of Suspension/ Bogie & Traction System

(b) Electric loco modeling, virtual modeling and simulation

Project-2: Laboratory for Development and evaluation of Power Electronics Applications (Setting up of PCB Lab)

Project-3: Software development Lab

Project-4: Laboratory for development and evaluation of Electrical Insulation Materials

·     Specifications for all projects finalized.

·     Detailed estimated sanctioned by GM/CLW.

·     NSR approved by Finance.

·     Special Conditions for Contract & Eligibility Criteria for all 04 projects prepared and approved by competent authority.

·     All cases forwarded to store for procurement.

·     Pre-bid conference held on 24.4.2017.

·     Tenders for all projects opened on 31.5.2017.

·     TR for all projects finalized. TC under finalization.

3.

Multi Traction Hybrid Passenger Locomotive (MTHPL)

·     A total 05 (five) Locomotives sanctioned by Railway Board (vide RSP 2016-17, Item No.1161).

·     Functional requirement Specification (FRS) prepared by RDSO.

·     Pre-application conference held on 19.03.2016 to facilitate the prospective manufacturers.

·     Expression of Interest (EOI) floated by CLW and 6 offers received.

·     Specification and Special Conditions of Contact finalized.

·     Detailed estimate and NSR approved.

·     Tender opened on 26.05.2017.

·     TR finalized. TC under finalization.


 

Sl. No

Project

 

Firm’s Name

P.O. No. / LoA No. & DP

Order

Qty.

Status

4.

Development of Hotel Load converter for WAP-7 Locomotive.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Siemens

As per Specification No. CLW/ES/3/IGBT/0490Alt C

P.O. No. 70/16/1125/ 10824 dated: 20.9.2016.

Amendment 02

Quantity increased from 17 loco sets to 22 locosets against 30% option clause.

17

sets

+05

sets

 

 

Material for all loco sets received at CLW.

 

16 loco sets dispatched.

 

Remaining 06 loco sets are under commissioning.

 

As per Specification No. CLW/ES/3/IGBT/ 0490 D

P.O. No. 70/19/1125/11150 dated: 30.08.2017.

Original DP: Prototype unit: 09 sets/month from P.O.

49 sets

Design document against Alt. D approved.

 

Supply yet to commence.

 

Medha

 

As per Specification No. CLW/ES/3/IGBT/ 0490 Alt C

P.O. No. 70/16/1125/ 10859 dated: 05.10.2016.

 

26  sets

All loco sets received at CLW.

Loco Nos. 30570, 30573, 30577 & 30578 dispatched in August’17 from CLW.

Under commissioning on loco Nos.  30575, 30576, 30579 & 30580.

P.O. issued.

33 sets

Supply yet to commence.

AAL

PO No. 70/2008/1125/ 00079  dt. 30/07/09

Original DP: Prototype unit: Within 01 year from P.O.

Extended DP: Extended up to 09.03.2015.

03 sets

Prototype unit commissioned on loco No. 30502 and dispatched to ELS/GZB in Nov’16.

Balance set to be supplied after field trial.

P.O. issued.

01 set

Supply yet to commence.

 

BHEL

PO No. 70/2008/1125/ 00081  dt. 05/08/09

Original DP: Prototype unit: Within 12 months from P.O.

1 Set

1st set commissioned on loco No. 30426 and dispatched to ELS/RPM in Aug.’15.

Field trials with dual hotel windings completed at Bangalore/Chennai alongwith RDSO.

PO No. 70/11/1125/00363

Dated: 02.08.12

Original DP: Prototype unit: Within 09 months from approval of design from RDSO.

03 sets

All loco sets received at CLW.

Under commissioning in loco Nos. 30597, 30598 & 30599.

 

 

70/16/1125/10823 dated: 20.9.2016.

Original DP:   Within 2 months from P.O. and @ 10 sets per quarter.

32

sets

Supply yet to commence.

 

P.O. issued.

17 sets

Supply yet to commence.

ABB

PO No. 70/11/1125/00344

Dated: 7.5.12

Original DP: Prototype unit: Offer of Prototype 03 months from approval of design.

Series Supply: @ 02 sets/ month.

03 sets

 

Prototype Unit commissioned on Loco No. 30510 and dispatched to ELS/BRCY in Dec’16.

01 set

Prototype clearance pending for field trial.

P.O. issued.

01 set

Supply yet to commence.

HIRECT

PO No. 70/16/1125/11005

Dated: 06.3.17

 

03 set

Design document  against Alt. C under approval.

P.O. issued.

01 set

Supply yet to commence.

Trolex

As per Specification No. CLW/ES/3/IGBT/ 0490B

LOA No. 70/15/1125A

Dated: 13.4.2015.

01  set

Provisional apparoval of test protocol, GA layout drawing and BOM accorded against Alt. A.

5.

Provision of Crew voice & video recording system on 3-ph passenger locomotives.

 As per Specn No.

RDSO/2015/EL/SPEC/0118 [Rev ’0’].

Trolex

P.O. No. 34/2017/2972/ 38096 dated: 21.08.2017.

Prototype unit: Prototype 03 months from the date of P. O.

Series Supply: Remaining sets within 06 months from prototype inspection i.e by 31.05.2018.

10 sets

Supply yet to commence.

Kayson

P.O issued.

5 sets

Supply yet to commence

Elixir

P.O issued.

3 sets

Supply yet to commence

6.

Indigenous development of IGBT based propulsion system.

 

Specification No. RDSO/2008/EL/

Spec/0071 Rev.5 issued in June’2016.

Medha

PO No. 70/12/1134/08209

dated: 07.05.12

 

05 sets

All Loco sets dispatched.

1st set commissioned on loco No. 31427 dispatched to ELS/LGD on 31.10.2013.

PO No. 70/14/1134/10402 dated: 12.8.2015.

24 sets

All Loco sets dispatched.

 

PO No. 70/16/1134/10869 dated: 20.10.2016.

Original DP: 1st 02 sets within 5 months. Balance qty. after 6 months @ 10 sets per quarter.

48 sets

Total 42 Loco sets supplied.

36 loco sets dispatched.

07 loco sets (loco Nos. 31938, 31939, 31961, 31942, 31948, 31945 & 31962) dispatched from CLW in August’17.

Under commissioning in loco Nos. 31949, 32002 & 32003.

ABB

PO No. 70/14/1134/10413 dated: 01.9.2015.

DP: Prototype unit: Within 06 months from P.O.

Series Supply: After approval of field trial by RDSO and to be completed within a quarter thereafter.

03 sets

Supply yet to commence.

PO No. 70/16/1134/10879 dated: 11.11.2016.

DP: Within 12 months from P.O.

01 set

Prototype unit commissioned on loco no. 31936 and dispatched in June’2017.

PO No. 70/17/1134/11054 dated: 19.05.2017.

DP: Within 06 months from P.O. @ 10 sets per quarter. To be completed by Feb’18.

17 sets

Supply yet to commence.

BHEL

PO No. 70/14/1134/10414 dated: 01.9.2015.

06 sets

All Loco sets dispatched.

 

PO No. 70/17/1134/11053 dated: 19.05.2017.

DP: Within 03 months from P.O. @ 10 sets per month.

66 sets

Preliminary Supply yet to commence.

Siemens

PO No. 70/14/1134/10570 dated: 04.2.2016.

DP: Within 12 months from P.O.

01 set

Preliminary design document submitted.

Supply yet to commence.

CGL

PO No. 70/16/1134/10892 dated: 25.11.2016.

Original DP:

Within 9 months from P.O.

01 set

Loco No. 31957 dispatched to ELS/GMO in July’17.

BTIL

PO No. 70/16/1134/10950 dated: 17.01.2017.

Original DP: Within 15 months from P.O.

01 set

Under commissioning in Loco No. 31985.

 

PO No. 70/18/1134/02/ 11104 dated: 08.07.2017.

DP: Within July’2017 preferably by 20 July’2017 urgently.

05 sets

Under commissioning on loco Nos. 31989, 31992, 31994, 31995 & 31996.

 

Developmental order has been placed for 01 loco-set each on following firms:

a.      M/s CRRC Pioneer Electric India Pvt. Ltd./Rewari/Haryana

b.      M/s  Titagarh Wagons Ltd./Kolkata

c.       M/s Hind Rectifier/Mumbai

d.      M/s Delta Power solutions India Pvt. Ltd./Rudrapur/Uttaranchal

e.      M/s Advance Rail Controls Pvt. Ltd./Bangalore

 

M/s Delta Power solutions India Pvt. Ltd. has submitted Revised Proforma-A & compliance to STR. Under scrutiny at CLW.

Design document of M/s CRRC under scrutiny.

7.

Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (200 Kmph)

(Rly. Bd’s L/No. 2007/Elect (TRS)/440/15 dated: 26.02.09).

 

 

M/s Arihant Electricals

Kol.

P.O. No. 91/10/0945/NS/ 00135 dated: 09/06/10

Original DP:

Prototype unit: 1 loco set within 06 months from PO.

Series Supply:

After 03 months from successful clearance of prototype for 06 months.

Extended DP: upto 31.3.14

2  sets

Prototype unit commissioned on loco No. 30086. Loco dispatched to ELS/GZB in Oct’15.

Field trial report of prototype unit received at CLW.

Dispatch clearance given for 2nd unit.

Material yet to be received at CLW.

 

8.

Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (160 Kmph).

 

 

M/s Arihant Electricals

Kol.

P.O. No. 91/10/0943/ 00096 dt.12/03/2010

Original DP: Prototype unit: 05 Nos. within 06 months from PO.

Series Supply: After 03 months from successful clearance of prototype for 18 months.

Extended DP: DP extended upto 31.3.15.

05  sets

Prototype unit commissioned in Loco No. 30056. Loco under commercial service since Dec’12 under ELS/BRCY.

2nd, 3rd and 4th set commissioned on loco No. 30087, 30090 & 30100 and sent to ELS/BRCY in Nov’15 & Jan’16 and ELS/GZB in March’16 respectively.

Balance set yet to be received at CLW.

Tender for 20 loco sets opened on 31.05.2017. TR finalized. TC under finalization.

9.

Indigenous development of TCN compliant vehicle control system through C-DAC.

(Pink Book No. 66 of 2012-13.)

C-DAC

MOU no. L 901118

dated 31/8/07

Original DP:

Project duration: 30 months.

 

 

02 sets

Commissioning has been completed in loco No. 31356 (WAG-9H). Loco dispatched to ELS/TKD. Performance found satisfactory.

Agreement for Transfer of Technology signed by CGL, ABB, AAL and BHEL with C-DAC.

2nd unit commissioned in loco No. 31778 and dispatched in August’16

10.

Vehicle Control Unit based on TCN open standard for 3-phase locomotives as per CLW specification No. CLW/C_D&D/ ES/3/TCN/0547 Dated: May’2016.

M/s ABB

P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.

Original DP:

Prototype unit: Within 03 months from PO.

Series Supply: After 03 months from date of clearance of prototype.

P.O. to be completed by 31.03.2018.

02 sets

To be increased to 04 sets

02 loco sets received at CLW.

Under commissioning in Loco Nos. 31951 & 31988.

 

M/s BHEL

P.O. No. 70/16/1142/ 11002 dated: 07.03.2017.

Original DP:

Prototype unit: Within 03 months from PO.

Series Supply: After 03 months from date of clearance of prototype. P.O. to be completed by 31.03.2018.

03 sets

To be  increased to 06 sets

Supply yet to commence.

P.O. No. 70/17/1142/ 11077 dated: 17.06.2017

Prototype unit: Within 06 months from PO.

Series Supply: 12 sets per quarter thereafter.

42 sets

Supply yet to commence

M/s CGL

P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.

Original DP:

Prototype unit: Within 03 months from PO.

Series Supply: After 03 months from date of clearance of prototype.

P.O. to be completed by 31.03.2018.

05 sets

To be  increased to 10 sets

All sets received at CLW.

1st unit commissioned in loco No. 30577 and dispatched to ELS/LGD in August’17.

Remaining under commissioning on loco Nos. 31946, 31974, 31986 & 31987.

 

P.O. No. 70/17/1142/ 11078 dated: 17.06.2017

Delivery: To commence from 01.04.2008 and would be completed by 31.12.2018.

28 sets

Supply yet to commence.

Tender No.70/18/1142 for 70 Loco sets opened on 08.08.2017. Under finalization.

11.

Remote Monitoring System for 3-phase Electric Locomotives (Specification No.

C-D&D/ES/3/0546)

 

 

 

150 sets

Tender opened on 10.05.2017.

Under finalization

 

12.

Development of Distributed Power Wireless Control System (DPWCS) for 3-phase electric loco. (P.B. item No. 37/ 2012-13.) Rly. Bd’s L/No. 2003/ Elect (TRS)/441 /8 dt. 29.12.06)

P.B. item no. 358/2012-13, 1122/2012-13.

M/s. ARC/

B’lore

LoA No. OT/ C-D&D/01/07/ 2007-08 dated 3rd June, 2008.

 

2 pair of locos

The prototype pairs have been installed in loco nos. 31282 (WAG-9) & 31284 (WAG-9). Loco has been put into commercial service w.e.f. 18.05.2012.

2nd set has been installed on Loco No. 31525 & 31526 and dispatched to ELS/TATA in Nov.’14.

Field trials completed. RDSO to give final clearance.

 

P.O. No. 70/16/1140/01088 dated: 28.06.2017.

Original DP:

Prototype unit: Within 06 months from PO.

Series Supply: @ 10 sets /month.

45 sets

Design document approved.

1st set received at CLW.

Under commissioning on loco No. 32101.

 

GE

P.O. No. 70/16/1140/01090 dated: 28.06.2017.

Prototype unit: Within 06 months from PO.

Series Supply: Within 06th  month of prototype clearance and to be completed by 12 months after issuance of P.O.

10 sets

Supply yet to commence.

Lotus

P.O. No. 70/16/1140/01089 dated: 28.06.2017.

Prototype unit: Within 06 months from the date of P.O. delivery.

Series Supply: @ 10 sets /month from 6th month of prototype clearance

20  sets

Supply yet to commence.

13.

IGBT based Composite Converter with Traction Converter and Hotel Load Converter for 3-ph WAP-5 locomotives as per Specification No. CLW/ES/IGBT/ 0518 Alt. B

ABB

P.O. No. 70/16/1136/ 10994 dated: 25.02.2017.

Original DP:

Prototype unit: Within 10 months from PO.

Series Supply: After 06 months from date of clearance of prototype.

10 sets

 

Mechanical dimension & basic design submitted by firm. Under finalization at CLW.

CGL

P.O. No. 70/16/1136/ 11016 dated: 23.03.2017.

Original DP:

Prototype unit: Within 12 months from PO.

Series Supply: After 03 months from date of clearance of prototype @ 3 sets /quarter.

05 sets

 

Supply yet to commence.

BHEL

P.O. No. 70/16/1136/ 10995 dated: 25.02.2017.

Original DP:

Prototype unit: Within 12 months from PO.

Series Supply: After clearance of prototype @ 2 sets /quarter.

05 sets

 

Supply yet to commence.

 

14.

Cab Upgradation of 3-phase locomotive.

 

 

 

FRS prepared.

EOI floated on 05.6.2017.

03 offers have been received.

15.

Complete Pantograph for 3 phase locomotives

 

 

 

EOI floated on 14.08.2017.

 

16.

Repair/Rehabilitation of motorized bogie of 3 phase locomotives at Loco sheds.

 

 

 

EOI to be floated.

               

 

 



Source : Welcome to CLW Official Website ! CMS Team Last Reviewed on: 05-09-2017  

  Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.